Tap any paragraph to write a margin note. Your notes collect in the Desk below the text and file under cases with @. The side-by-side margin rail opens on a larger screen.

Code · CFR · Title 40 — Protection of Environment · Part 63 · § 63.1187

§ 63.1187. What do I need to know about operations, maintenance, and monitoring plans?

377 words·~2 min read·/us/cfr/t40/s§ 63.1187·

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

(a)An operations, maintenance, and monitoring plan must be submitted to the Administrator for review and approval as part of your application for the title V permit.
(b)The operations, maintenance, and monitoring plan must include the following:
(1)Process and control device parameters you will monitor to determine compliance, along with established operating levels or ranges for each process or control device.
(2)A monitoring schedule.
(3)Procedures for properly operating and maintaining control devices used to meet the standards in §§ 63.1178 and 63.1179 of this subpart. These procedures must include an inspection of each incinerator at least once per year. At a minimum, you must do the following as part of an incinerator inspection:
(i)Inspect all burners, pilot assemblies, and pilot sensing devices for proper operation. Clean pilot sensor if necessary.
(ii)Ensure proper adjustment of combustion air, and adjust if necessary.
(iii)Inspect, when possible, all internal structures (such as baffles) to ensure structural integrity per the design specifications.
(iv)Inspect dampers, fans, and blowers for proper operation.
(v)Inspect motors for proper operation.
(vi)Inspect, when possible, combustion chamber refractory lining. Clean, and repair or replace lining if necessary.
(vii)Inspect incinerator shell for proper sealing, corrosion, and/or hot spots.
(viii)For the burn cycle that follows the inspection, document that the incinerator is operating properly and make any necessary adjustments.
(ix)Generally observe whether the equipment is maintained in good operating condition.
(x)Complete all necessary repairs as soon as practicable.
(4)Procedures for keeping records to document compliance.
(5)Corrective actions you will take if process or control device parameters vary from the levels established during performance testing. For bag leak detection system alarms, example corrective actions that may be included in the operations, maintenance, and monitoring plan include:
(i)Inspecting the fabric filter for air leaks, torn or broken bags or filter media, or any other condition that may cause an increase in emissions.
(ii)Sealing off defective bags or filter media.
(iii)Replacing defective bags or filter media, or otherwise repairing the control device.
(iv)Sealing off a defective fabric filter compartment.
(v)Cleaning the bag leak detection system probe, or otherwise repairing the bag leak detection system.
(vi)Shutting down the process producing the particulate emissions.
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.